Expansion of the ferry port

Expansion of the ferry port

Status and planning for the Project per June-September 2020

The Construction work for the expansion of the ferry port in Karlshamn, in order to accomodate for the new generation ferries with a length of 230 metres, has started.

During the period June- August 2020 there will mainly be Heavy Construction work. Initially various earhwork including transportation of stones and gravel. Demolition of the old quay and drilling will occur. Further on also steel piling will start up gradually and continue for a longer period. During the Holiday season week 28-31 all work will kept at a lower level. During week 32 a working barge will arrive for the piling and costruction ot the mooring Dolphins. Work will mainly be performed on- and around the location for the new RoRo-berth (3) and the breakwater pier (7).
Information about the proceedings will be given continously throughout the Project.

In other Words, there is "Full speed ahead", in order to welcome DFDS new ferries as from July 1:st 2021.